Table 2 Research period

After/before Period Duration Key events Number of postings
Before construction of the park Period 1 2013. 06. 01.∼2014. 05. 31. 2013. 06. Establishment of Gyeongui Line Forest Park Development Plan 2013. 10. Start of construction of Gyeongui Line Park Project Phase 2 3,104
Period 2 2014. 06. 01.∼2015. 05. 31. 2015. 05. Completion of construction of Phase 2 9,870
After construction of the park Period 3 2015. 06. 01.∼2016. 05. 31. 2015. 09. Start of construction of Gyeongui ∼ine Park Project Phase 3 2016. 05. Completion of construction of whole Gyeongui Line Park Project 21,883
Period 4 2016. 06. 01.∼2017. 05. 31. 2016. 06.∼2016. 07. Complementary construction based on viewpoints of park users 35,588