Table 5.
Working hours for each street tree management item

Street tree pruning Unit Quantity (diameter at breast height cm), per tree
11 less 11-21 less 21-31 less 31-41 less 41-51 less 51 or more
Heavy pruning Working time min 6.3 12.4 15.6 22.4 32.4 42.3
Work preparation time min 12.2 12.2 12.2 12.2 12.2 12.2
Travel time min 1.8 1.8 1.8 1.8 1.8 1.8
Workload per hour week 2.96 2.27 2.03 1.65 1.29 1.07
Daily workload week 23.65 18.18 16.22 13.19 10.34 8.53
Light pruning Working time min 11.3 16.7 21.4 29.4 38.9 57.4
Work preparation time min 12.2 12.2 12.2 12.2 12.2 12.2
Travel time min 1.8 1.8 1.8 1.8 1.8 1.8
Workload per hour week 2.37 1.95 1.69 1.38 1.13 0.84
Daily workload week 18.97 15.64 13.56 11.06 9.07 6.72
Shrub pruning Unit Obstacle area, per 10m2 of planting area
Less 0.9m 0.9m or more
Working time min 3.4 5.8
Work preparation time min 2.4 2.4
Travel time min 0.03 0.03
Workload per hour m2 102.92 72.90
Daily workload m2 823.33 583.23
Watering of water sprinkler truck Unit Water tank (water sprinkler truck), per 1.5m2 of planting area
1,800L 3,800L 5,500-6,500L
Working time min 3.7 2.5 1.7
Work preparation time min 1.4 1.4 1.4
Travel time min 1.2 1.2 1.2
Workload per hour m2 142.86 176.47 209.30
Daily workload m2 1,142.86 1,411.76 1,674.42
Weeding Unit Obstacle area, per 1.5m2
Working time min 6.1
Work preparation time min 5.6
Travel time min 0.03
Workload per hour m2 51.15
Daily workload m2 409.21
Tree fertilization Unit Quantity (diameter of root / unit: cm), per 1 week
11 less 11-21 less 21-31 less 31-41 less 41-51 less 51 or more
Working time min 5.1 5.8 6.7 8.2 9.3 11.6
Work preparation time min 1.3 1.3 1.5 1.5 1.7 1.7
Travel time min 0.03 0.03 0.03 0.03 0.03 0.03
Workload per hour m2 9.33 8.42 7.29 6.17 5.44 4.50
Daily workload m2 74.65 67.32 58.32 49.33 43.52 36.01
Shrub fertilization Unit Obstacle area, per 1m2 of planting area
Working time min 9.4
Work preparation time Min 2.1
Travel time min 0.03
Workload per hour m2 52.04
Daily workload m2 416.31
Chemical spraying (machine) Unit Obstacle area, chemical spraying amount per 1,000ℓ
Working time min 73.5
Work preparation time min 42.3
Travel time min 73.5
Workload per hour per vehicle 1.06
Daily workload per vehicle 8.45
Windbreak wall installation Unit Quantity (tree height), per 10m
H = 0.45m H = 0.9m
Working time min 4.6 6.4
Work preparation time min 3.3 4.2
Travel time min 0.03 0.03
Workload per hour m2 7.57 5.64
Daily workload m2 60.53 45.16