Table 9.
Comparison of standard of estimated unit and actual construction cost

Classification Unit Standard of estimated unit Actual construction cost Rate (%)
Street tree pruning Heavy pruning 11 less per tree 62,919 71,603 88
11-21 less per tree 89,693 93,119 96
21-31 less per tree 120,638 104,406 116
31-41 less per tree 148,451 128,391 116
41-51 less per tree 178,874 163,663 109
51 or more per tree 229,847 198,582 116
Light pruning 11 less per tree 38,529 89,239 43
11-21 less per tree 58,462 108,286 54
21-31 less per tree 80,250 124,864 64
31-41 less per tree 102,560 153,081 67
41-51 less per tree 124,807 186,590 67
51 or more per tree 146,595 251,843 58
Shrub pruning Less 0.9m m2 9,016 11,973 75
0.9m or more m2 14,873 16,902 88
Watering of water sprinkler truck 1,800L m2 1,157 797 145
3,800L m2 807 655 123
5,500-6,500L m2 424 498 85
Weeding m2 1,259 1,362 92
Tree fertilization 11 less per tree 6,249 8,069 77
11-21 less per tree 7,910 8,947 88
21-31 less per tree 9,395 10,328 91
31-41 less per tree 11,012 12,210 90
41-51 less per tree 12,498 13,841 90
51 or more per tree 14,159 16,727 85
Shrub fertilization m2 1,567 1,447 108
Chemical spraying(machine) L 263,092 212,182 124
Windbreak wall installation H = 0.45m m 12,660 14,118 90
H = 0.9m m 17,464 18,925 92