Table 16. Business implementation schedule

Schedule Main contents Note
2017 April - September Receipt of private proposals -
2017 December - 2018 October Round table (1st, 2nd, 3rd) and notification of acceptance of proposal Preferred negotiator selection
2019 October Deliberation by the Urban Planning Committee -
2019 November City Park Committee deliberation -
2019 December Agreement signed -
2020 January Deposit payment -
2020 February Business designation notice -
2020 March Determination of park development plan and announcement of topographical drawings -
2020 June Implementation plan approval notice and land compensation notice -
2021 March Urban management plan (use area) decision (change) -
2021 June Appointment of general planner -
2021 August Implementation of construction project management (design stage) service -
2022 June Construction scheduled to start -
2024 December Construction to be completed -