Division | Apartment-A | Apartment-B | Apartment-C | Apartment-D | Apartment-E | Apartment-F | Apartment-G |
---|---|---|---|---|---|---|---|
Location | Urban reconstruction project district (Gyeonggi-do) | Urban development project district (Gyeonggi-do) | Urban development project district (Gyeonggi-do) | Urban development project district (Gyeonggi-do) | Public housing development project district (Gyeonggi-do) | Urban development project district (Gyeonggi-do) | Public housing development project district (Gyeonggi-do) |
Construction period | 2016.11.24.-2020.05.31. | 2014.10.27.-2017.08.30. | 2013.02.07.-2015.07.15. | 2012.11.15.-2015.07.14. | 2017.12.01.-2020.06.30. | 2014.05.01.-2016.06.30. | 2017.10.13.-2020.05.24. |
Construction days | 1,260 days | 1,039 days | 889 days | 960 days | 943 days | 792 days | 955 days |
Site area | 50,360m2 | 93,799m2 | 75,260m2 | 70,930m2 | 43,549m2 | 34,633m2 | 27,340m2 |
Building area | 9,207m2 | 22,276m2 | 9,795m2 | 9,383m2 | 5,452m2 | 4,923m2 | 4,137m2 |
Landscaping area | 17,842m2 | 28,842m2 | 22,590m2 | 31,245m2 | 13,501m2 | 11,401m2 | 8,202m2 |
Number of households | 2,003 | 2,701 | 1,442 | 1,414 | 712 | 690 | 447 |
Supervision service company | Supervision-1 | Supervision-2 | Supervision-3 | Supervision-4 | Supervision-5 | Supervision-6 | Supervision-7 |
Relevant laws | Apartment building construction project under the building act |