Table 15. Construction project management (detail design) business scope

Item Construction project management business scope
Design stage

Review the suitability of various related plans and calculation standards (specifications, guidelines, laws, etc.)

Review whether sufficient prior opinions from local civil petitioners have been collected

Review the relevant laws and regulations applicable to the task, prepare and operate the construction project management procedure, and review the suitability of design standards and construction standards (standards and specialized specifications)

Review of adequacy of detailed design (draft)

Reviewing the suitability of the selection of the applied method, materials used, and various types of performance improvement

Business support in case of civil complaints or litigation related to detailed design

Review of adequacy of installation of auxiliary facilities (ventilation facilities, lighting, disaster prevention facilities, drainage facilities, landscaping, etc.)

Confirmation of adequacy of construction and adequacy of maintenance plan

Review and confirm whether the structural calculation of facilities, etc. is appropriate

Whether the design drawings and structural calculations are consistent and appropriate (including whether reinforcing bars are appropriate, etc.)

Review and confirm the adequacy of the contents of the investigation (surveying, local conditions, ground condition, obstacles, sluice gates, various materials, etc.)

Review and confirm whether the results of the on-site investigation are properly applied to the design

Review of recommendations for use of new methods, new technologies, and special methods

Additional correction instructions for omissions, errors, and unclear parts in the design document

Review of the implementation of the matters reviewed by the Parks Committee and the Urban Planning Committee

Implement the procedures for introducing and registering computerized programs in accordance with relevant laws, and check whether the user uses the program after verifying it

Review of adequacy of drawing

Review of the appropriateness of the construction specifications

Periodic construction project management (design stage) result report

Local confirmation and inspection of matters stipulated in the guidelines (Ministry of Land, Infrastructure and Transport) for design competition, implementation of basic design, etc. and review of economic feasibility of design

Check whether the various design documents (reports, specifications, drawings, structural statements, load statements, statements, quantity calculations, etc.) match

Check and submit the results of the computer program for major structures

Review of adequacy of maintenance design

Review of seismic design

Review of conformity with design standards

Stability review when connecting with existing structures and dismantling existing structures

Review how to relocate various obstacles such as landscaping trees and whether the relocation period is appropriate

Review of economic feasibility (VE) and project cost adequacy of detailed design

When a designer subcontracts, review whether it is legal or appropriate

Create a designer’s work log and review the contents

Review of adequacy of construction period and construction cost (lifecycle cost)

Preparation of result reports on construction project management

If you have no experience in applying major structures, or to prevent safety accidents when applying construction methods, etc., research, analyze, and review similar domestic and foreign cases, prepare an optimal (draft), and reflect the design

When drafting construction specifications, prepare standard drafts for safe construction by hazardous and risky work type and work stage, and prepare precautions before, during, and after construction

Review the adequacy and content of the design safety report advisory meeting in accordance with Article 75-2 of the Enforcement Decree of the Construction Technology Promotion Act

Support for review of adequacy and contents of underground safety impact assessment and environmental impact assessment and consultation with related organizations

Review of design content adequacy and completion rate for previously prepared design documents

When other additional tasks occur, the ordering party and the contracting party will discuss and decide